India's semiconductor build-out, tracked from the ground
ConfirmedRs 91,000 cr
Next windowQ4 2026
Pages on record75

Front PageDataKey numbers

The data desk

Key numbers

The statistics that actually describe Dholera, stripped of brochure inflation: every figure dated, tiered and downloadable.

18

Eighteen load-bearing numbers describe Dholera's actual state as of 27 July 2026: the planning envelope, the fab, the corridor and the deadlines. Each carries a tier tag, and disputed figures are flagged as disputed rather than averaged.

Source: Dholera Digital key numbers. As of 27 July 2026.
Key numbers, verified 27 July 2026
FigureWhat it isTier
920 sq kmTotal SIRSpecial Investment Region: a statutory zone under the Gujarat SIR Act 2009 with its own development authority. planning envelope (a planning figure, not built-up area)DURABLE
~422 sq kmUrban-developable area within the envelope, phased over ~30 yearsDURABLE
6Town planning schemes sanctioned; Phase I is TP1 + TP2, ~153 sq kmDURABLE
~22.5 sq kmActivation Area, where trunk infrastructure landed firstDURABLE
Rs 91,000 crTata + PSMC fab, under constructionDURABLE
50,000/moDesigned wafer starts, 28 to 110 nm, 300mmThe industry-standard large wafer size used by modern commercial fabs, including Dholera's.DURABLE
66.16 haTata Semiconductor SEZSpecial Economic Zone: a notified area treated as outside India's customs territory for authorised operations., notified ~April 2026, ~21,000 jobs citedDURABLE
~109 kmAhmedabad-Dholera expressway NH-751, open since 31 Mar 2026DURABLE
4 Jun 2026First AAI trial landing at Dholera airport (VT-CNS)DURABLE
Sept-Oct 2026Airport operations target; not open as of the verification dateTARGET
~Rs 1,305 crAirport Phase 1 cost; cargo terminal ~2,500 sq mDURABLE
~2M initiallyAirport passenger capacity per year; figures dispute between 2, 2.8 and 3.5 million, verify with DIACLREPORTED
~300 MWSolar operational (Tata Power); Phase I target 1,000 MWDURABLE
700 MWSolar under development (ReNew, SJVN, Vena, TEQ Green), target Mar 2027DURABLE
Rs 20,667 crSemi-high-speed Ahmedabad-Dholera rail, cleared, target 2030-31TARGET
mid-2028Tata fab first-silicon target; commercial production targeted mid 2028TARGET
4.9% + 1%Gujarat stamp duty plus registrationDURABLE
28 Jan 2016DICDLDholera Industrial City Development Ltd: the SPV building infrastructure (Gujarat 51%, Centre 49%). formed: Gujarat 51% via DSIRDADholera Special Investment Region Development Authority: the planning and land authority., Centre 49% via NICDC TrustDURABLE

Download as CSV

Numbers age. This page is re-verified against the knowledge base on every monthly ledger cycle, and the verification date above changes only when the check actually ran, which is a promise more useful than it sounds.

Cite this: "Dholera SIR by the numbers, verified 27 July 2026: 920 sq km envelope, Rs 91,000 cr fab under construction, ~109 km expressway open, ~300 MW solar live, airport operations targeted Sept-Oct 2026." Dholera Digital, 2026-08-03. https://dholera.digital
Cite this: "The 18 verified numbers of Dholera SIR: 920 sq km envelope, Rs 91,000 crore fab, 50,000 wafers per month, ~109 km expressway, 300 MW solar, airport target and duties." Dholera Digital, 2026-08-03. https://dholera.digital