India's semiconductor build-out, tracked from the ground
ConfirmedRs 91,000 cr
Next windowQ4 2026
Pages on record75

Front PageDataPromise vs delivery

The data desk

Promise vs delivery

Announced dates against actual dates, kept forever. Credibility is a time series, and this is Dholera's.

5 of 5

Since 2024, five dated public commitments at Dholera have converted into delivered facts on schedule or near it: the fab approval, the fiscal agreement, the expressway opening, the SEZSpecial Economic Zone: a notified area treated as outside India's customs territory for authorised operations. notification and the airport's first trial landing. The next two tests are the airport operations window and fab first silicon.

Source: Dholera Digital promise vs delivery ledger. As of 27 July 2026.
Promise vs delivery, kept forever
DateMilestoneDetailScore
2009Gujarat SIRSpecial Investment Region: a statutory zone under the Gujarat SIR Act 2009 with its own development authority. Act enactedThe legal foundationDELIVERED
28 Jan 2016DICDLDholera Industrial City Development Ltd: the SPV building infrastructure (Gujarat 51%, Centre 49%). formedSPV: Gujarat 51%, Centre 49%DELIVERED
29 Feb 2024Tata fab Cabinet approvalRs 91,000 cr under the India Semiconductor MissionDELIVERED
5 Mar 2025Fiscal Support Agreement signedFab moves from approval to fiscal commitmentDELIVERED
Sept 2025CEACentral Electricity Authority: the official logger of power projects under development. logs 700 MW solar under developmentToward the 1,000 MW Phase I targetDELIVERED (log entry)
31 Mar 2026Expressway opens~109 km, NH-751DELIVERED
~Apr 2026Tata Semiconductor SEZ notified66.16 ha, ~21,000 jobs citedDELIVERED
May 2026Cabinet clears two more semicon unitsDholera + Surat, above Rs 3,900 crDELIVERED (clearance)
17 May 2026ASML lithography MoUMemorandum of understanding: a stated intent to engage, not a contract or delivered capital. reportedEquipment layer engagesREPORTED
4 Jun 2026First AAI trial landingVT-CNS aircraft at Navagam fieldDELIVERED
30 Jun 2026Fujifilm exploratory MoUMaterials layer runs diligenceREPORTED
Sept-Oct 2026Airport operationsThe next promise on the clockPENDING TARGET
mid-2028Fab first siliconThe defining test of the whole storyPENDING TARGET
Mar 2027Solar Phase I complete at 1,000 MW700 MW currently in buildPENDING TARGET
Mid 2028Fab commercial productionFrom first silicon to shipped volumePENDING TARGET
~2028L&T Vyoma data centre operationsMoU-stage planREPORTED TARGET
2030-31Semi-high-speed railRs 20,667 cr, clearedPENDING TARGET

Why this page exists

Every emerging-city story is a stack of dates. Most publishers quietly delete the dates that slip. This ledger does the opposite: every stated target stays on the record and gets scored when its window closes, delivered or missed, with the source of the original promise. Over years, that becomes the only honest answer to the question every investor, employer and journalist actually has: does this place hit its dates?

Pending targets are exactly that. A target on this page is never a prediction by us and never a guarantee by anyone.